PENERAPAN BUILDING INFORMATION MODELING (BIM) PADA PENJADWALAN ULANG PROYEK PEMBANGUNAN GEDUNG PUSDIK HIDROS

SABILLAH MAHARANI, . (2025) PENERAPAN BUILDING INFORMATION MODELING (BIM) PADA PENJADWALAN ULANG PROYEK PEMBANGUNAN GEDUNG PUSDIK HIDROS. Sarjana thesis, UNIVERSITAS NEGERI JAKARTA.

[img] Text
COVER.pdf

Download (1MB)
[img] Text
BAB 1.pdf

Download (119kB)
[img] Text
BAB 2.pdf
Restricted to Registered users only

Download (356kB) | Request a copy
[img] Text
BAB 3.pdf
Restricted to Registered users only

Download (702kB) | Request a copy
[img] Text
BAB 3.pdf
Restricted to Registered users only

Download (702kB) | Request a copy
[img] Text
BAB 4.pdf
Restricted to Registered users only

Download (3MB) | Request a copy
[img] Text
BAB 5.pdf
Restricted to Registered users only

Download (107kB) | Request a copy
[img] Text
DAFTAR PUSTAKA.pdf

Download (244kB)
[img] Text
LAMPIRAN.pdf
Restricted to Registered users only

Download (2MB) | Request a copy

Abstract

Penelitian ini berjudul “Penerapan Building Information Modeling (BIM) pada Penjadwalan Ulang Proyek Pembangunan Gedung Pusdik Hidros”, yang merupakan studi kasus pada bangunan pendidikan bertingkat empat seluas 3.200 m² yang difungsikan sebagai pusat pendidikan dan pelatihan, dengan struktur utama berupa beton bertulang. Penelitian ini dilatarbelakangi oleh adanya kebutuhan percepatan progres pekerjaan dari pihak pemilik proyek. Penjadwalan sebelumnya masih menggunakan metode konvensional yang tidak mampu merepresentasikan hubungan antaraktivitas secara menyeluruh dan tidak menyediakan visualisasi proses konstruksi secara real-time. Penelitian ini bertujuan untuk menyusun penjadwalan ulang proyek secara lebih sistematis dan terintegrasi menggunakan teknologi Building Information Modeling (BIM) berbasis 4D. Metode yang digunakan adalah Research and Development (R&D) dengan pendekatan model pengembangan 4D, yang terdiri dari tahapan Define, Design, Develop, dan Disseminate. Penyusunan jadwal dilakukan melalui Microsoft Project, yang kemudian diintegrasikan dengan model tiga dimensi (struktur, arsitektur, dan MEP) dalam Autodesk Navisworks guna menghasilkan simulasi penjadwalan visual berbasis waktu. Hasil penelitian menunjukkan bahwa penjadwalan ulang berbasis BIM 4D dinyatakan layak oleh validator ahli karena mampu meningkatkan efisiensi dan akurasi jadwal proyek, yang ditunjukkan dengan penurunan durasi pelaksanaan dari 197 hari kalender menjadi 133 hari kalender, sehingga menghasilkan penghematan waktu sebesar 64 hari. Kata kunci: Building Information Modeling, BIM 4D, Penjadwalan Ulang, Simulasi Visual, Navisworks.***** This study, entitled "Application of Building Information Modeling (BIM) in the Rescheduling of the Pusdik Hidros Building Construction Project," is a case study of a four-story educational facility covering 3,200 m², functioning as a center for education and training, with reinforced concrete as its primary structural system. The research was initiated due to the owner's request to accelerate project progress. The initial scheduling used conventional methods, which failed to represent the interrelationships among project activities comprehensively and lacked real-time construction process visualization. This study aimed to develop a more systematic and integrated project rescheduling approach using 4D-based Building Information Modeling (BIM) technology. The method employed was Research and Development (R&D) with a 4D development model approach, consisting of the stages: Define, Design, Develop, and Disseminate. The scheduling was carried out using Microsoft Project and then integrated with a three-dimensional model (structure, architecture, and MEP) in Autodesk Navisworks to produce a time-based visual scheduling simulation. The results show that the 4D BIM-based rescheduling is validated as feasible by expert validators, as it improves both the efficiency and accuracy of project scheduling. This is demonstrated by a reduction in project duration from 197 calendar days to 133 calendar days, resulting in a time savings of 64 days. Keywords: Building Information Modeling, BIM 4D, Rescheduling, Visual Simulation, Navisworks.

Item Type: Thesis (Sarjana)
Additional Information: 1). Adhi Purnomo, M.T. ; 2). Mirara Khanza, M.T.
Subjects: Teknologi dan Ilmu Terapan > Teknik Sipil
Teknologi dan Ilmu Terapan > Konstruksi Bangunan
Divisions: FT > D IV Teknologi Rekayasa Konstruksi Bangunan Gedung
Depositing User: Sabillah Maharani .
Date Deposited: 13 Aug 2025 01:06
Last Modified: 13 Aug 2025 01:06
URI: http://repository.unj.ac.id/id/eprint/59277

Actions (login required)

View Item View Item