PENGEMBANGAN METODE PEMASANGAN DAN PEMBONGKARAN BEKISTING SEMI-KONVENSIONAL DENGAN 5S UNTUK EFISIENSI WAKTU PEKERJAAN STRUKTUR GEDUNG BERTINGKAT (STUDI KASUS:PROYEK THE PRASADA ANTASARI)

MUHAMMAD FADHLURRAHMAN, . (2026) PENGEMBANGAN METODE PEMASANGAN DAN PEMBONGKARAN BEKISTING SEMI-KONVENSIONAL DENGAN 5S UNTUK EFISIENSI WAKTU PEKERJAAN STRUKTUR GEDUNG BERTINGKAT (STUDI KASUS:PROYEK THE PRASADA ANTASARI). Sarjana thesis, UNIVERSITAS NEGERI JAKARTA.

[img] Text
COVER.pdf

Download (1MB)
[img] Text
BAB 1.pdf

Download (623kB)
[img] Text
BAB II-dikompresi.pdf
Restricted to Registered users only

Download (1MB) | Request a copy
[img] Text
BAB III.pdf
Restricted to Registered users only

Download (2MB) | Request a copy
[img] Text
BAB IV-dikompresi.pdf
Restricted to Registered users only

Download (4MB) | Request a copy
[img] Text
BAB V.pdf
Restricted to Registered users only

Download (193kB) | Request a copy
[img] Text
DAFTAR PUSTAKA.pdf

Download (202kB)
[img] Text
Lampiran Disertasi compres.pdf
Restricted to Registered users only

Download (4MB) | Request a copy

Abstract

Pekerjaan pemasangan dan pembongkaran bekisting pada proyek gedung bertingkat memiliki peran strategis dalam menentukan kinerja waktu pekerjaan struktur karena bersifat repetitif pada setiap siklus lantai dan berada pada jalur kritis proyek. Pada Proyek The Prasada Antasari Office ditemukan adanya deviasi progres pekerjaan struktur yang salah satunya dipengaruhi oleh durasi pekerjaan bekisting yang lebih lama dari rencana. Permasalahan tersebut disebabkan oleh penataan material yang tidak terorganisir, tidak adanya sistem penandaan komponen bekisting, serta alur pengangkutan material yang tidak terencana, sehingga menimbulkan pemborosan waktu kerja. Penelitian ini bertujuan untuk mengembangkan metode pemasangan dan pembongkaran bekisting semi-konvensional yang lebih efisien dari sisi waktu serta menganalisis peningkatan efisiensi melalui perbandingan durasi antara metode eksisting dan hasil pengembangan metode. Penelitian menggunakan pendekatan Research and Development (R&D) dengan model Four-D (Define, Design, Develop, Disseminate). Pengembangan metode dilakukan dengan mengintegrasikan prinsip 5S (Seiri, Seiton, Seiso, Seiketsu, Shitsuke), melalui perbaikan penataan material, sistem penandaan (marking) komponen bekisting, pembuatan terminal pengangkutan (staging area), serta penyusunan urutan kerja yang lebih sistematis. Efisiensi waktu dianalisis menggunakan metode studi waktu (time study) dengan menghitung waktu normal dan waktu standar, kemudian membandingkan durasi pekerjaan antara metode eksisting dan hasil pengembangan metode. ***** The installation and dismantling of formwork in high-rise building projectsplays a strategic role in determining the performance of structural work becauseit is repetitive in each floor cycle and is on the critical path of the project. InThePrasada Antasari Office Project, there was a deviation in the progress of structural work, one of which was influenced by the duration of formwork work that waslonger than planned. This problem was caused by disorganized material arrangement, the absence of a formwork component marking system, andunplanned material transportation flows, resulting in wasted work time. This study aims to develop a semi-conventional formwork installationanddismantling method that is more time-efficient and to analyze the increaseinefficiency by comparing the duration between the existing method andthedeveloped method. The study uses a Research and Development (R&D) approachwith a Four-D model (Define, Design, Develop, Disseminate). The methodwasdeveloped by integrating the 5S principles (Seiri, Seiton, Seiso, Seiketsu, Shitsuke) through improvements in material arrangement, a marking systemfor formworkcomponents, the creation of a staging area, and the development of a moresystematic work sequence. Time efficiency was analyzed using the time studymethod by calculating normal and standard times, then comparing the durationof work between the existing method and the developed method.

Item Type: Thesis (Sarjana)
Additional Information: 1). Ir. Tri Mulyono, M.T. ; 2). Selvia Agustina, S.T., M.T.
Subjects: Teknologi dan Ilmu Terapan > Teknik Sipil
Teknologi dan Ilmu Terapan > Konstruksi Bangunan
Divisions: FT > D IV Teknologi Rekayasa Konstruksi Bangunan Gedung
Depositing User: Muhammad Fadhlurrahman .
Date Deposited: 24 Aug 2026 01:32
Last Modified: 24 Aug 2026 01:32
URI: http://repository.unj.ac.id/id/eprint/72139

Actions (login required)

View Item View Item