PEMBUATAN VIDEO METODE FAST TRACK UNTUK MENGATASI KETERLAMBATAN PELAKSANAAN PROYEK PEMBANGUNAN INSTALASI GAWAT DARURAT RUMAH SAKIT UMUM DAERAH DR. SOESELO SLAWI

HIDAYATUL AULIA, . (2024) PEMBUATAN VIDEO METODE FAST TRACK UNTUK MENGATASI KETERLAMBATAN PELAKSANAAN PROYEK PEMBANGUNAN INSTALASI GAWAT DARURAT RUMAH SAKIT UMUM DAERAH DR. SOESELO SLAWI. Sarjana thesis, UNIVERSITAS NEGERI JAKARTA.

[img] Text
COVER.pdf

Download (1MB)
[img] Text
BAB I.pdf

Download (442kB)
[img] Text
BAB II.pdf
Restricted to Registered users only

Download (661kB) | Request a copy
[img] Text
BAB III.pdf
Restricted to Registered users only

Download (663kB) | Request a copy
[img] Text
BAB IV.pdf
Restricted to Registered users only

Download (4MB) | Request a copy
[img] Text
BAB V.pdf
Restricted to Registered users only

Download (324kB) | Request a copy
[img] Text
DAFTAR PUSTAKA.pdf

Download (336kB)
[img] Text
LAMPIRAN DAN DAFTAR RIWAYAT HIDUP.pdf
Restricted to Registered users only

Download (3MB) | Request a copy

Abstract

Abstrak. Proyek pembangunan Instalasi Gawat Darurat Rumah Sakit Umum Daerah Dr. Soeselo Slawi mulai dilaksanakan pada tanggal 14 Juli 2023 dan direncanakan selesai pada tanggal 10 Desember 2023. Pada saat dilakukan penelitian, laporan progres mingguan proyek hingga minggu ke-4 menunjukan keterlambatan pelaksanaan proyek sebesar 1,388%. Hal tersebut berpotensi terhadap keterlambatan waktu penyelesaian akhir proyek, dan kontraktor berisiko terkena sanksi atas keterlambatan tersebut. Berdasarkan hal tersebut, maka dilakukan percepatan menggunakan metode Fast Track menggunakan Microsoft Project serta mengembangkannya menjadi video tutorial. Tujuan pembuatan video tutorial adalah sebagai media yang menyajikan informasi untuk mengatasi keterlambatan pelaksanaan proyek. Metode penelitian dan pengembangan produk yang dilakukan adalah menggunakan metode 4D (Define, Design, Development, dan Disseminate). Hasil penelitian ini berupa penjadwalan metode Fast Track dan video tutorial. Berdasarkan penerapan metode Fast Track tingkat kemajuan proyek kembali pada rencana semula sehingga proyek dapat selesai sesuai kontrak yaitu 150 hari. Adapun hasil produk ini adalah video tutorial. Video yang dikembangkan sudah melalui tahapan validasi kelayakan dengan 2 ahli yaitu ahli materi dan ahli media. Validasi media video tutorial memperoleh katergori layak dengan revisi ditinjau berdasarkan hasil validasi. Pada aspek materi memperoleh persentase 77,77% dan pada aspek media video memperoleh persentase sebesar 90% dengan kategori sangat layak. ***** Abstract. The construction Project of The Emergency Department of The Regional General Hospital (RSUD) Dr. Soeselo Slawi began on July 14, 2023 and is planned to be completed on December 10, 2023. At the time of the research, the weekly project progress report until week 4 showed a 1,388% delay in project implementation. This has the potential to delay the final completion time of the project, and the contractor risks being penalized for the delay. Based on this, acceleration is carried out using the Fast Track method using Microsoft Project and developing it into a video tutorial. The purpose of making video tutorials is as a medium that provides information to overcome delays in project implementation. The product research and development method used is the 4D method (Define, Design, Development, and Disseminate). Based on the application of the Fast Track method, the project progress level returned to the original plan so that the project could be completed according to the contract, namely 150 days. The result of this product is a video tutorial. The video being developed must go through a feasibility validation stage with 2 experts, namely a material expert and a media expert. Validation of the video tutorial media obtained an appropriate category with revisions reviewed based on the validation results. In the material aspect, the percentage was 77.77% and in the video media aspect, the percentage was 90%, with a very decent category.

Item Type: Thesis (Sarjana)
Additional Information: 1). Dr. Ir. Irika Widiasanti, M.T. ; 2). Lenggogeni, M.T.
Subjects: Teknologi dan Ilmu Terapan > Teknik Sipil
Divisions: FT > D IV Teknologi Rekayasa Konstruksi Bangunan Gedung
Depositing User: Users 25169 not found.
Date Deposited: 09 Aug 2024 03:44
Last Modified: 09 Aug 2024 03:44
URI: http://repository.unj.ac.id/id/eprint/49484

Actions (login required)

View Item View Item