PENJADWALAN ULANG PROYEK KONSTRUKSI DENGAN PEMANFAATAN BIM PADA PROYEK REHAB TOTAL GEDUNG SEKOLAH SMPN 117 JAKARTA

ARI IKHSAN WICAKSONO, . (2025) PENJADWALAN ULANG PROYEK KONSTRUKSI DENGAN PEMANFAATAN BIM PADA PROYEK REHAB TOTAL GEDUNG SEKOLAH SMPN 117 JAKARTA. Diploma thesis, UNIVERSITAS NEGERI JAKARTA.

[img] Text
File COVER.pdf

Download (631kB)
[img] Text
File BAB 1.pdf

Download (309kB)
[img] Text
File BAB 2.pdf
Restricted to Registered users only

Download (399kB) | Request a copy
[img] Text
File BAB 3.pdf
Restricted to Registered users only

Download (559kB) | Request a copy
[img] Text
File BAB 4.pdf
Restricted to Registered users only

Download (1MB) | Request a copy
[img] Text
File BAB 5.pdf
Restricted to Registered users only

Download (240kB) | Request a copy
[img] Text
File Daftar Pustaka.pdf

Download (210kB)
[img] Text
File Lampiran.pdf
Restricted to Registered users only

Download (342kB) | Request a copy

Abstract

Penelitian ini berjudul “Penjadwalan Ulang Proyek Konstruksi dengan Pemanfaatan BIM: Studi Kasus Rehab Total Gedung Sekolah SMPN 117 Jakarta”. Metode yang digunakan adalah penelitian deskriptif kualitatif dengan pendekatan Research and Development (R&D) menggunakan model pengembangan 4D, yang terdiri dari tahap Define, Design, Develop, dan Disseminate. Pada tahap Define, dipetakan permasalahan keterlambatan proyek akibat perubahan desain (elevasi lantai 1) atas permintaan pihak owner, Dinas Pendidikan Provinsi Jakarta. Keterlambatan menyebabkan jadwal awal selama 28 minggu (14 Agustus 2024–23 Februari 2025) menjadi 59 minggu (hingga 28 September 2025). Tahap Design dilakukan penjadwalan ulang menggunakan perangkat lunak Microsoft Project berbasis data Material Take Off dari model BIM 3D, AHSP PUPR 2025, dan jadwal baseline. Hasil perancangan menunjukkan total durasi proyek menjadi 390 hari. Pada tahap Develop, jadwal ulang dikolaborasikan dengan model BIM 3D (struktur, arsitektur, dan MEP) dan disimulasikan dalam bentuk BIM 4D menggunakan Navisworks. Simulasi ini memvisualisasikan urutan pekerjaan secara rinci dan mendukung komunikasi proyek. Penjadwalan ulang terbukti lebih efisien dengan pengurangan durasi 4,87% dibandingkan jadwal awal (410 hari). Terakhir, tahap Disseminate dilakukan melalui penyebaran hasil produk kepada Dinas Pendidikan Provinsi Jakarta dalam bentuk poster berisi pranala produk melalui kode barcode. ***** This research is entitled "Construction Project Rescheduling with BIM Utilisation: Case Study of Total Rehab of SMPN 117 Jakarta School Building". The method used is descriptive qualitative research with a Research and Development (R&D) approach using the 4D development model, which consists of the Define, Design, Develop, and Disseminate stages. At the Define stage, the problem of project delays due to design changes (1st floor elevation) at the request of the owner, the Jakarta Provincial Education Office, was mapped. The delay caused the initial schedule for 28 weeks (14 August 2024-23 February 2025) to become 59 weeks (until 28 September 2025). The Design stage was rescheduled using Microsoft Project software based on Material Take Off data from the 3D BIM model, AHSP PUPR 2025, and the baseline schedule. The design results showed the total project duration to be 390 days. At the Develop stage, the reschedule was collaborated with 3D BIM models (structure, architecture, and MEP) and simulated in the form of 4D BIM using Navisworks. This simulation visualises the sequence of work in detail and supports project communication. The rescheduling proved to be more efficient with a 4.87% reduction in duration compared to the original schedule (410 days). Finally, the Disseminate stage was carried out through the distribution of product results to the Jakarta Provincial Education Office in the form of posters containing product links through barcode codes.

Item Type: Thesis (Diploma)
Additional Information: 1). Adhi Purnomo, M.T. ; 2). Muh Abdhy Gazali HS, M.T.
Subjects: Teknologi dan Ilmu Terapan > Teknik Sipil
Teknologi dan Ilmu Terapan > Konstruksi Bangunan
Divisions: FT > D IV Teknologi Rekayasa Konstruksi Bangunan Gedung
Depositing User: Ari Ikhsan Wicaksono .
Date Deposited: 12 Aug 2025 03:27
Last Modified: 12 Aug 2025 03:27
URI: http://repository.unj.ac.id/id/eprint/60003

Actions (login required)

View Item View Item