CHRISTOFER, . (2017) PENGENDALIAN WAKTU PRODUKSI BALOK GIRDER DENGAN MENGGUNAKAN METODE CPM DAN LoB (Studi Kasus Pada PT. Adhi Karya (Persero) Pabrik Precast Sentul). Sarjana thesis, UNIVERSITAS NEGERI JAKARTA.
Text
BAB II.pdf Download (847kB) |
|
Text
ABSTRACT.pdf Download (6kB) |
|
Text
ABSTRAK.pdf Download (115kB) |
|
Text
BAB I.pdf Download (196kB) |
|
Text
COVER.pdf Download (26kB) |
|
Text
BAB IV.pdf Download (825kB) |
|
Text
BAB V.pdf Download (73kB) |
|
Text
BAB III.pdf Download (322kB) |
|
Text
DAFTAR PUSTAKA.pdf Download (9kB) |
|
Text
DAFTAR ISI.pdf Download (57kB) |
|
Text
DAFTAR LAMPIRAN.pdf Download (4kB) |
|
Text
DAFTAR GAMBAR.pdf Download (70kB) |
|
Text
DAFTAR TABEL.pdf Download (50kB) |
|
Text
KATA PENGANTAR.pdf Download (89kB) |
|
Text
lembar pengesahan.pdf Download (381kB) |
|
Text
Lembar Pernyataan.pdf Download (363kB) |
|
Text
RIWAYAT HIDUP.pdf Download (17kB) |
Abstract
Penelitan ini bertujuan mengendalikan waktu produksi Balok Girder dengan menggunakan metode CPM (Critical Paht Method) dan LoB (Line of Balance) guna mendapatkan jumlah produksi maksimal dengan penyesuaian waktu yang tepat. Penelitian ini menggunakan metode perhitungan dan pengelolaan data sekunder dan primer yang digambarkan pada grafik dan diagram. Studi kasus proyek pembangunan jalan layang LRT (Light Rail Transit), pada tempat produksi balok girder PT. Adhi Karya Pabrik Precast Sentul Dari hasil penelitian menunjukkan kemampuan produksi balok girder meningkat sebanyak 21 unit balok girder perbulan dengan kecepatan lintasan 59,4286 Unit per jam , balance delay 42,3678% line efficiency 42,267 %, dengan waktu siklus yang digunakan sebanyak 68.5 jam pada siklus pertama, 69 jam pada waktu siklus kedua, 69 jam pada waktu siklus ketiga, 69 jam waktu siklus keempat dan memiliki waktu tunggu yang terjadi pada setiap pergantian siklus sebesar 1 jam. Sehingga hasil penelitian tersebut dapat dinyatakan bahwa terjadi percepatan produksi dengan menggunakan metode CPM (Critical Path Method) dan LoB (Line of Balance) sebesar 10 jam per bulan. This research is purpose to control time in Girder beam production using CPM (Crticial Path Method) and LoB (Line of Balance) to get maximum productions amount with time adaptibility precisely. This research is using count method and management of secondary and primary data that illustrated to graphic and diagram. Case study at project of building the overpass LRT (Light Rail Transit), to productions girder beam at PT. Adhi Karya Factory Precast Sentul. The result of this research shows that productions capability girder beam increase as much 21 unit girder beam per month with speed track 59,4286 unit per hour, balance delay is 42,3678%, line efficiency 42,267 with time cycle that using is 68,5 hours in first cycle, 69 hours in second cycle, 69 hours in third cycle, 69 hours in fourth cycle and having waiting time that happen to every turn of cycle is one hour. So that the result of research can declare is happen productions acceleration with using CPM (Critical Path Method) and LoB (Line of Balance) is 10 hour per month.
Item Type: | Thesis (Sarjana) |
---|---|
Additional Information: | 1) Anisah, MT 2) Adhi Purnomo, MT |
Subjects: | Teknologi dan Ilmu Terapan > Teknik Sipil |
Divisions: | FT > S1 Pendidikan Teknik Bangunan |
Depositing User: | sawung yudo |
Date Deposited: | 28 Jun 2022 06:29 |
Last Modified: | 28 Jun 2022 06:29 |
URI: | http://repository.unj.ac.id/id/eprint/30871 |